Multiply length by width by thickness — all in feet — then divide by 27, because a cubic yard is 27 cubic feet. A 10 × 12 slab at 4 inches thick is 10 × 12 × 0.333 ÷ 27, or 1.48 cubic yards.

“Yardage” on a job site means cubic yards, and it is the unit every ready-mix plant quotes in. The arithmetic is three multiplications and a division. The step that catches people is the thickness.

The formula

cubic yards = length ft × width ft × thickness ft ÷ 27

The 27 is exact — NIST Handbook 44’s general tables of units of measurement defines a cubic yard as 27 cubic feet exactly — so the only places error creeps in are your measurements and the thickness you actually pour. Background on mix design and placing is published by the Portland Cement Association.

Thickness is almost always given in inches and must be converted first:

ThicknessIn feet
3 in0.25
4 in0.333
5 in0.417
6 in0.5
8 in0.667
12 in1.0

Using 4 instead of 0.333 makes the answer twelve times too big. It is the single most common error in a concrete estimate.

Concrete calculator
01 / PROJECT DIMENSIONS
Length
Width
Waste %%

Change any measurement to update your estimate.

02 / YOUR MATERIAL ESTIMATE
You need approximately
1.23 cubic yards
33.33 ft³ of concrete
With 5% waste: 1.3 cubic yards (recommended when ordering)
40 lb bags
112 bags
50 lb bags
89 bags
60 lb bags
75 bags
80 lb bags
56 bags
Open the full concrete calculator →

Worked example: a 10 × 12 slab

At 4 inches:

  1. Area: 10 × 12 = 120 ft²
  2. Thickness in feet: 4 ÷ 12 = 0.333
  3. Cubic feet: 120 × 0.333 = 40 ft³
  4. Cubic yards: 40 ÷ 27 = 1.48 yd³

Add 5–10% and order 1.6 yd³ — in practice, 1.75 yards, since plants sell in quarter-yard increments.

Square yards is a different thing

A square yard is 9 square feet of flat area. It tells you nothing about how much concrete to order, because it has no thickness in it. Contractors sometimes price finishing by the square yard, which is where the confusion starts.

square yards = ft² ÷ 9        (area — for finishing labour)
cubic yards  = ft³ ÷ 27       (volume — for ordering concrete)

That 10 × 12 slab is 13.3 square yards and 1.48 cubic yards. Order 13.3 yards of concrete and nine trucks will show up.

Bags or ready-mix

An 80 lb bag of concrete mix yields about 0.6 ft³, so a cubic yard takes 45 of them.

Bag sizeYieldBags per cubic yard
40 lb0.30 ft³90
50 lb0.375 ft³72
60 lb0.45 ft³60
80 lb0.60 ft³45

The 10 × 12 slab at 4 inches is 40 ft³ — 67 bags of 80 lb mix. That is the point where bagging stops making sense. Past about 50 bags, order ready-mix: hand-mixing that volume takes a full day and risks cold joints between batches, which show as permanent seams in the finished surface.

The concrete calculator does this for slabs, and there are fixed-size slab pages if yours is a standard footprint.

Footings and odd shapes

Break the pour into rectangles and add the volumes:

ElementDimensionsCubic feet
Slab10 × 12 × 0.33340.0
Thickened edge44 lin ft × 0.5 × 0.511.0
Total51.0 ft³ = 1.89 yd³

For a round footing or sonotube, use π × radius² × depth. A 12-inch tube 4 feet deep is 3.14 × 0.5² × 4 = 3.14 ft³, so nine of them is just over a cubic yard.

Why you always round up

You cannot pause a pour to make more concrete. A short load means a cold joint you will see forever; a surplus is a wheelbarrow of waste. Order to the next quarter yard, dampen the subgrade before the truck arrives, and set your forms dead level — concrete finds every low spot and fills it at your expense.

Calculators in this article